Location: 4464 W. Plano Pkwy, Plano, TX
System Size: 600kW (4 x 150kW modular system)
Goal: Fully operational, revenue-generating, grid-connected ultra-fast charging station

Overall Feasibility Score: 33/40 (High Interest)

The property at 4464 W. Plano Pkwy presents a strong opportunity for EV charging infrastructure, given its strategic location, ample space, operational compatibility, and supportive city infrastructure.

Timeframe Growth rate

Month 1-6 12-18 sessions/day (5-10%)

Month 7-12 25-35 sessions/day (10-15%)

Month 13-24 40-55 sessions/day (15-25%)

Month 25-36 60-80 sessions/day (25-30%)

Revenue Projections (Based on $0.55/kWh, Avg. 35kWh per session)

  • Year 1: $250K - $500k

  • Year 2: $500K - $800K

  • Year 3: $1M +

⚡️ Installation Process ⚡️

Phase 1: Feasibility Assessment

Owner: Project Manager (PM), Utility Liaison

  • ✅ Conduct topographic and civil survey of property

  • ✅ Perform load study and utility capacity check

  • ✅ Validate zoning/commercial code compliance

  • ✅ Coordinate with Oncor to start new service process

  • ✅ Prepare site readiness for MEP

🛠️ Deliverable: Feasibility report and site readiness checklist

Phase 2: System Design & Permitting

Owner: Project Manager (PM),Engineering firm, City Liaison

  • ⚙️ Electrical load and layout design (conduits, transformers, panels)

  • 📐 CAD plans for trenching, pad mounts, solar (if included), canopies and signage

  • 🗂 Submit permit packages for:

    • Electrical

    • Civil

    • Structural (if canopies or enclosures are added)

  • 📝 Secure approvals from local fire marshal and building inspectors

🛠️ Deliverable: Approved stamped construction plans, permit application

Phase 3: Procurement & Pre-Construction

Owner: Procurement Manager, GC, OEM Rep, Project Manager (PM)

  • 🔌 Place orders for:

    • 600kW of DC fast chargers (4 x 150KW)

    • Power cabinet(s), switchgear, meter/main panel

    • Network controller + hardware

  • 🛒 Schedule delivery of pads, bollards, trenching gear, and signage

  • 👷 Select GC and electrical subcontractors

  • 📅 Lock in construction schedule with OEM support

🛠️ Deliverable: All components ordered, contractor mobilized,

Phase 4: Civil & Electrical Construction

Owner: GC, Electrical Contractor, Utility Crew, Project Manager (PM)

  • 🚧 Mobilization, fencing, and safety setup

  • ⛏ Trenching for conduits, transformer pads, power cable runs

  • 🪛 Pour pads and mount chargers

  • 🔌 Install switchgear, meter panel, and communications

  • 🧰 Pull wiring, set transformers, integrate rectifier.

🛠️ Deliverable: Physical installation complete, pre-commissioning checklist signed

Phase 5: Utility Interconnection & Commissioning

Owner: Utility Rep, OEM, Project Manager (PM)

  • 📞 Schedule meter set and transformer energization with Oncor

  • ⚡️ OEM team arrives for system commissioning and power-up

  • 🔄 Test each charging port for uptime, speed, payment, and safety

  • 📲 Test PulsePoint integration, remote monitoring, CX features

🛠️ Deliverable: Full system go-live, signed off by city and utility

Phase 6: Launch Preparation & Operations

Owner: Marketing Lead, Ops Manager

  • 📢 Finalize signage, paint striping, station lighting

  • 🎯 Promote launch date across channels

  • 💳 Validate customer workflows: QR scan, app launch, payment, support

  • 👥 Train on-site staff if applicable

  • 🔁 Monitor first-week load and uptime

🛠️ Deliverable: Charging station live and public-facing, launch press ready